Redeveloping Berths 6 and 8, and providing over 800 feet of additional moorage will help ensure the long-term viability of the Port as the home to the North Pacific Fishing Fleet while improving the marine environment by removing creosote timber pilings.
Project Overview
This project redeveloped Berths 6 and 8 along the northeast side of Pier 90. Improvements include pile replacement, a new wharf structure, a new float system, bulkhead improvements, and office consolidation for operations, fishing and industry customers. The new berths are equipped with shore power for fishing and industrial vessels. Key aspects of the project are:
- Demolition of over 62,000 square feet of condemned or load-restricted timber apron and 830 linear feet of seawall (northerly portion of Berth 6 and entire Berth 8)
- Construction of a new, high-capacity (650 psf) pier tailored to fishing vessel and industrial customers, including applicable utilities, bollards, and steel fender system
- Improvements to the marine environment, including the removal of over 2,200 creosote timber pilings and installation of a stormwater treatment system, and increased functionality without increasing the pier's overwater coverage
Purpose
The purpose of this project is asset and revenue preservation.
Business Plan Objectives
- Bring Berths 6 and 8 back into service for large fishing vessels (and other customers) with improved berth efficiency and access
- Provide more flexibility to accommodate a variety of vessel sizes
Century Agenda
This project supports the Port’s Century Agenda by restoring capabilities of Pier 90 structure similar to the remaining Terminal 91 aprons.
Permitting
This project requires environmental permitting and review. Permits/approvals include:
- State Environmental Policy Act (SEPA) Review
- City of Seattle Shoreline Substantial Development Permit
- City of Seattle Construction Permit
- US Army Corps of Engineers Permit
- Washington Department of Fish and Wildlife Hydraulic Permit Approval
- Washington Department of Ecology Section 401 Water Quality Certification
Timeline
| Commission construction authorization | Q3 2023 |
| Construction starts | Q3 2024 |
| Open for use | Q4 2026 |
Estimated Project Costs
Total authorization for this project is $104 million.